Linking WBS, CPM, and Budget

Effective project control begins when scope, time, and cost are connected through a common structure — the Work Breakdown Structure (WBS).

1. The Integration Triad

Linking WBS, CPM, and Budget

2. Linking Process

  1. Each WBS element is assigned a unique code.
  2. Activities in the CPM network are mapped to corresponding WBS items.
  3. Each WBS item is associated with a budget line item (cost code).
  4. The result: a unified control framework for time–cost tracking.

Example:

Linking Process

This integration enables automatic generation of:

  • Cost-loaded schedules
  • Earned Value reports
  • Forecasts and performance dashboards
“Control begins when WBS, schedule, and budget speak the same language.”

Category: Construction Academy

Subcategory: Budgeting and Planning

Subcategory: Construction Phase

Subcategory: Design Coordination

Subcategory: Estimation Techniques

Subcategory: Initiation and Feasibility

Subcategory: Introduction

Subcategory: Personal Management

Subcategory: Project Close-Out

Subcategory: Project Scheduling

Subcategory: Project Teams

Subcategory: Proposal Management

Subcategory: Total Quality Management

Subcategory: Tracking and Control

Subcategory: Work Breakdown

Category: Help Desk

Subcategory: Client

Subcategory: Construction 101

Subcategory: Contractor Management

Subcategory: Expense

Subcategory: Finance Budget

Subcategory: Inventory Management

Subcategory: My Approvals

Subcategory: Site Management

Subcategory: Vendor Management